November 12, 2026
On Friday, Oct. 23, Google Fiber work in Chatham Forest broke a gas line. On the next workday, Monday, Oct. 26, another gas line broke in Chatham Forest and a water line broke on East Street, Chapelboro reported. That made three utility strikes in two workdays. The Town of Pittsboro then stopped all Google Fiber work across town.
Work restarted Nov. 3 with a new list of rules. One rule sets aside the stretch from Thanksgiving week through New Year's. Between Friday, Nov. 13, and Jan. 4, the Town's schedule leaves 18 weekdays when fiber crews may dig anywhere in town. Downtown gets 13. The tree lighting, First Sunday, and the Christmas week closures all land in the gaps.
The strikes in late October came after earlier warnings. The News & Observer reported that the Town first told residents about its concerns on Sept. 18. It issued stop-work orders on Oct. 8 for Chatham Forest and for Beacon Drive, where a water main had broken. The paper also reported that Town inspectors found "holes, open vaults and cable left out of construction sites." The contractor, Hyper Networks, was told to clean up sites, fill holes and close vaults downtown and in neighborhoods.
On Monday, Nov. 2, Development Services Director Maie Armstrong led an all-hands safety briefing and work plan review. Google Fiber, Hyper Networks and other utilities working in the area attended. The Town then allowed work to resume Nov. 3. The conditions came from its Fourth Corrective Action Notice and from improvements listed in Google Fiber's own investigation report. The Town's announcement sets the terms for how crews work on your street:
The last item on the list carries the most weight for the season. No contractor may do Google Fiber work during set stoppage periods. Downtown, those are Nov. 5-9, Dec. 4-7 and Dec. 17-21. Townwide, they are Nov. 9-12, Nov. 19-30, Dec. 10-14, Dec. 23-28 and Dec. 30-Jan. 4. The Town says these dates "correspond with scheduled Town holidays, closures, and special events." WRAL covered the restart and the new rules on Nov. 3.
The first two stoppage windows have passed, and both lined up with the calendar. The downtown pause from Nov. 5 to 9 included Saturday, Nov. 7, when the Chatham Mills Farmers Market moved to its winter hours, 10 a.m. to 1 p.m. on the lawn in front of Chatham Mills. The townwide pause from Nov. 9 to 12 ends today. It covered Veterans Day on Wednesday, when Town Hall was closed and Pittsboro Health and Rehab held its Honoring our Veterans morning on Chatham Business Drive.
| Dates | Google Fiber digging | On the calendar |
|---|---|---|
| Nov. 13-18 | Allowed on weekdays, townwide | None listed |
| Nov. 19-30 | Paused townwide | Tree Lighting in Downtown Pboro, Sun., Nov. 22; Town Hall closed Nov. 26-27 for Thanksgiving |
| Dec. 1-3 | Allowed townwide | None listed |
| Dec. 4-7 | Paused downtown | Brightspeed's Merry + Bright at MOSAIC, Sat., Dec. 5; First Sunday, Dec. 6 |
| Dec. 8-9 | Allowed townwide | Sip & Shop for the Holidays at Vino!!, Wed., Dec. 9, evening |
| Dec. 10-14 | Paused townwide | Town-designated stoppage |
| Dec. 15-16 | Allowed townwide | None listed |
| Dec. 17-21 | Paused downtown, allowed elsewhere on weekdays | Town-designated stoppage |
| Dec. 22 | Allowed townwide | None listed |
| Dec. 23-28 | Paused townwide | Town Hall closed Dec. 23-25 for Christmas |
| Dec. 29 | Allowed townwide | None listed |
| Dec. 30-Jan. 4 | Paused townwide | Town-designated stoppage |
The longest pause is the 12 days from Nov. 19 to 30. On Sunday, Nov. 22, from 3 to 7 p.m., Vino!! Wine Shop at 89 Hillsboro St. hosts the Tree Lighting in Downtown Pboro. Its listing calls the event annual and promises Santa, food trucks, entertainment, a train ride, a bounce house and a vendor market. The Thanksgiving closure of Town Hall on Nov. 26 and 27 also falls in this window, so no townwide fiber work is allowed for the whole week.
The first weekend of December has a lot on it. On Saturday, Dec. 5, from 6 to 8 p.m., MOSAIC at Chatham Park hosts Brightspeed's Merry + Bright Christmas Drone Light Show at the Philip H. Kohl MOSAIC Family Commons, 457 Freedom Pkwy. The evening includes a holiday market with more than 30 vendors, Santa photos, train rides and crafts. On Sunday, Dec. 6, from noon to 4 p.m., the Pittsboro Business Association's First Sunday market sets up at the Pop-Up Park, 50 W. Salisbury St. That Sunday falls inside the Dec. 4-7 downtown pause. The Friday before and the Monday after are also off-limits for fiber work downtown.
Some evening events fall on weekdays when crews are allowed to dig, and the daily hours keep the two apart. Vino!!'s Sip & Shop for the Holidays runs Wednesday, Dec. 9, from 6 to 9 p.m. By then, fiber work has had to be shut down for an hour.
Count the weekdays the Town left open and the season looks short. From now until the end of November, fiber crews may dig on four days: Friday, Nov. 13, and Monday through Wednesday, Nov. 16-18. December has 14 open weekdays townwide: Dec. 1-4, 7-9, 15-18, 21, 22 and 29. Downtown has nine, because the downtown pauses remove Dec. 4, 7, 17, 18 and 21. Even on those days, crews may close a lane for only two hours, split between late morning and early afternoon.
Neighborhoods outside downtown will see the most work. Of the 18 open weekdays townwide, five are closed downtown, all in December. GFiber's Triangle page asks people to check service availability by address.
The fiber stoppage list covers Google Fiber and its contractors. A separate project begins this week. The Town announced that Enbridge Gas expected to start relocating its gas lines along Hillsboro Street the week of Nov. 9. Enbridge is doing this work, not NCDOT, and it has to be finished before the road widening can start. Drivers should expect single-lane closures on weekdays between 9 a.m. and 4 p.m. No full road closures are planned. The announcement gives Enbridge its own hours and no list of stoppage periods. On Hillsboro Street, that means the quiet fiber weeks may still have lane closures for the gas work.
The gas relocation clears the way for NCDOT's widening project, TIP R-5724B. It runs about 1.8 miles from Launis Street to Powell Place Lane. The NCDOT presentation to the Board of Commissioners on Jan. 12, 2026 lists an added east-side sidewalk from Thompson Street to Launis Street, improvements to the Salisbury Street intersection, and downtown streetscape work. The Chatham News & Record reported that the widened street will have two 12-foot lanes with a continuous center turn lane, a five-foot sidewalk on the west side, and a 10-foot multi-use path on the east side.
The schedule has moved since January. That presentation projected a construction letting in summer 2026 and completion in winter 2028. The Town's Nov. 6 announcement now says construction on the full roadway project is scheduled to begin in January 2028.
Once that construction begins, downtown's holiday stretch will be protected again, by a rule set long before the fiber dispute. The NCDOT presentation limits downtown pedestrian improvements to January 15 through September 30 so that work stays clear of seasonal events. It also says the contractor will meet with business owners before starting. Any closure of Hillsboro Street downtown is limited to overnight work on underground water, sewer and drainage lines. The Town's share of the downtown streetscape is already paid for. In February, the Town announced it had secured $1.95 million in total: $850,000 in federal Community Project Funding, $850,000 from the North Carolina Department of Commerce's Rural Downtown Economic Development Grant, and $250,000 from the Town budget.
The stoppage dates are part of the Town's corrective action requirements. Crews are also required to notify residents before they arrive on a street. For concerns about Google Fiber work, the Town directs residents and businesses to Development Services Director Maie Armstrong at [email protected] or (984) 282-6706. The News & Observer reported that Google Fiber also gave residents a 24-hour construction line, (877) 454-6959. The Town posts its notices on its news page, and you can sign up for alerts at pittsboronc.gov/notifyme.
For more on how MOSAIC and Hillsboro Street work together on a weekend, see our August look at Pittsboro, or browse the Pittsboro neighborhood page.
If you're thinking about putting your home on the market, starting a renovation or planning a move, and you want to know how the Hillsboro Street timeline affects your plans, Nev Nelson is glad to go over the dates with you and help you pick the right window. Let's Connect.
Stay up to date on the latest real estate trends.
Whether you are a first-time buyer, a seasoned investor, or somewhere in between, I bring Raleigh / Triangle market knowledge and personal attention that make all the difference. I take time to understand your goals and tailor every step of the process to fit your needs. From strategy to closing, I ensure you feel confident and well-informed throughout your real estate journey.